Queensway Tunnel:
Grand plans

Diagram of tunnel proposal, 1924
Diagram of tunnel proposal, 1924

If it were being built today, a 44ft (13m) diameter tunnel under a river estuary, with two branches, underwater junctions and four tunnel portals to be squeezed into city centre locations would be an incredibly large-scale project.

In 1923, the only viable prospect was to have it excavated by hand. No tunnel of comparable diameter had been built before, and nothing existed to match its length or its complexity. No ground surveys could be carried out. No mechanism existed by which central government could plan such large-scale schemes. The railways, which held enormous political sway, were vociferous opponents, given that they operated the only existing river crossing. The odds were, really, stacked against it.

All the same, the Mersey Tunnel Joint Committee was formed in 1923 and within a little more than two years work had started. When it opened, it was the engineering marvel of the world.

Schemes and squabbles

By the time any road crossing was planned, the Mersey had already been crossed once with the Mersey Tunnel, a railway tunnel opened in 1886. Most of the goods, vehicles and luggage from the busy ports were forced to cross by the various ferries and steamers — many owned by Liverpool and Birkenhead's Corporations — that did the short trip across the river.

By the 1920s cross-river traffic was increasing sharply. In 1922, 62,000,000 foot passengers made the trip, double the number twenty years previously. The vehicle figures made an even sharper leap, from 36,000 in 1901 to 640,000 in 1921. Something needed to be done, and the three options proposed were a bridge, a tunnel or an improved ferry service.

Routes for proposed bridge (blue) and tunnel (red), circa 1923. Click to enlarge
Routes for proposed bridge (blue) and tunnel (red), circa 1923. Click to enlarge

The bridge plan was short-lived. The suspension bridge (shown in blue on the map above) would have to be of a sufficient height to clear shipping and its main span would be more than 3,000ft (900m). When the proposal was publicised in September 1923, the tunnel was costed at £6,400,000 while the bridge was £10,550,000. The resulting working party was therefore named the Mersey Tunnel Joint Committee.

A route for a tunnel. Click to enlarge
A route for a tunnel. Click to enlarge

Initially the tunnel was to connect the ferry terminals and little more, looping around so that its entrances were on the waterfront. At its western end, a lengthy spur was proposed running along the river bed to reach Wallasey, some way to the north.

The map to the right (click to see it full-size) appeared alongside an article in the Liverpool Daily Courier in September 1924. It clearly shows how each branch of the tunnel was to go directly to an existing cross-river ferry terminal.

The route of the tunnel was the least of the Committee's worries. By March 1924, the cost had risen to £7,250,000 and a deputation to Whitehall returned with the news that the government would offer one third of the total cost, on the condition that there were no tolls. The offer was far below what was required and Sir Archibald Salvidge, the leader of the Committee, vowed to fight on.

By September that year, the Road Fund was offering half the £6,500,000 cost, on the basis that it considered anything above this amount to be paying for the tram lines, which the Road Board was not authorised to do. Liverpool said no again and demanded 75% of the cost, not including the tramway provision. It was an uphill struggle, not least because Birkenhead and Wallasey were completely unwilling to offer any funds towards the project.

Early plans for tunnel layout at Liverpool. Click to enlarge
Early plans for tunnel layout at Liverpool. Click to enlarge

In March 1925, Birkenhead offered funding on the strict condition that no trams were to be run in the tunnel. Wallasey offered some selfish conditions which were rejected, and so the lengthy (and costly) Wallasey branch was unceremoniously dropped. The scheme proceeded as a Birkenhead and Liverpool joint project. With the trams gone, a suggestion was made that horse traffic use the lower deck.

Birkenhead tunnel entrance proposals. Click to enlarge
Birkenhead tunnel entrance proposals. Click to enlarge

Eventually — on the pretext of employment relief — the government awarded a grant of 75% of the total costs and work started almost immediately, with the tolls retained and the tramway space built for future use. One has to wonder whether they agreed simply to stop the endless deputations being sent from Merseyside.

It was only in November 1925 that the configuration of tunnel entrances was fixed — as evidenced by a plan drawn earlier that year (see above and left; click to enlarge), which shows three alternative termini in Birkenhead. The Rendel Street branch was at one point to be the main terminus; and it was only very late in the day that the current main entrance was chosen over the preferred riverfront one.

The following month, Princess Mary Viscountess Lascelles attended George's Dock in Liverpool to formally start work. The Mersey road tunnel was underway.

Going underground

The construction of the tunnel was an incredible feat, involving 1,700 workers. Seventeen of them died in the process. Work was mainly carried out by hand or by small power tools, and it was only after some tentative experiments when the tunnel was already under way that explosives began to be used. Progress was slow and excavation appears to have taken six years, from December 1925 to some time in 1931.

Work progressed from each side of the Mersey, and in 1928 the pilot tunnels met beneath the river. The incredible precision with which the work was carried out meant that the two tunnels were less than an inch off-line. It was a tribute to the skill of the project's engineers — but then the roll-call of civil engineers who worked on the project is essentially a list of great names in British engineering. One of them, Basil Mott, founded the company Mott & Hay, which went on to build the Channel Tunnel, and now in the guise of Mott MacDonald still carries out work on the Queensway Tunnel to this day.

Fitting out the interior of the tunnel — in particular the four-lane road deck suspended across the centre of the bore — took several years more, and it was eventually opened on July 18th 1934 by King George V. The Liverpool Daily Post published an enormous supplement to celebrate the event, including the following pictures and information.

Picture credits

  • Photographs of construction and opening from a Liverpool Daily Post supplement published 16 July 1934, now believed to be out of copyright.

With thanks to Iain Ellis for information on this page.

In this section

What's new

A century of motorways

It's 100 years since the opening of the world's first motorway, the Autostrada from Milan to the Lakes.

Schrödinger’s speed limit

In 2022, Manchester City Council say they reduced the speed limit on the Mancunian Way to 30mph. But it’s not clear if they did. It’s not even clear if they can.

Sorry, wrong number

Road numbering is a system with clear rules. What happens when the people responsible for numbering roads don't follow them?

Share this page

Have you seen...

Major incidents

What happens when there's a big accident on a trunk route? Who picks up the pieces, and why does it take so long?

About this page

Published

Last updated