Scheme outline
Work to improve the capacity of the roundabout at M4 junction 16 west of Swindon. The roundabout is already fully signalised and in order to provide space for more traffic and support nearby planned developments reconstruction work is now being carried out.
The changes will see a right-turn introduced from the A3102 Swindon Road and the B4005 Hay Lane on the south side of the roundabout which will bypass the junction completely, and changes to the A3102 Great Western Way to the north including remodelling of the next set of traffic signals towards Swindon.
Timescale
Cost
Status
Type
Highway authority
Funding
Progress
More information
Is this page out of date? These pages work entirely through your contributions. If you can provide information on what's happening, you can submit a progress update above. If information on this page is inaccurate or out of date, then please send us a message so we can correct it.
The roadworks are complete and the roundabout is running on its new alignment. Signal timings and minor work (landscaping etc) to be completed.