A90 Balmedie - Tipperty

Scheme outline

Upgrade of the existing A90 between Balmedie and Tipperty to dual two-lane standard, with provision of two new grade separated junctions. This will complete a gap in the existing dual carriageway that currently forms a major bottleneck.

This scheme was completed in and we're no longer accepting updates or changes to this page.

Timescale
Spring 2015 - Winter 2017
Cost
£
53m
Status
Completed
Type
Bypass or realignment
for use by all traffic
Highway authority
Funding
Scottish Executive

Progress

This scheme has been completed and we are no longer accepting progress updates.
14 June 2006

A public exhibition for the plans has been held.

14 January 2007

Transport Scotland has announced its preferred route for the road.

14 July 2008

Transport Scotland is now issuing Compulsory Purchase Orders for the land the new road will require, even though the statutory process is not yet complete. The start of work has been set back two years to 2010.

16 August 2009

Local inquiry is due to start on 18 August 2009.

29 August 2010

A local newspaper quotes the Transport Minister as saying a final decision is expected by the end of the year.

27 January 2011

In a news item released today, Transport Scotland has confirmed that this project will now definitely go ahead.

6 December 2011

According to the Infrastructure Investment Plan released today, this project will be combined with the Aberdeen Western Peripheral Route into a single package for the purposes of funding and delivery.

15 March 2012

The Made Orders were published today.

22 October 2014

Work has started on this road.

20 February 2015

The official start of construction was marked by a visit from the First Minister on 16 February 2015, according to the Transport Scotland website.

13 December 2016

Opening has now been delayed from Spring 2017 to Winter 2017/2018, according to the Scottish Government.

29 May 2018

The northbound carriageway has now opened, albeit in a contraflow configuration. Completion of the AWPR project as a whole is expected autumn 2018, with the Balmedie - Tipperty section likely to open in the summer.

13 August 2018

Balmedie to Tipperty section will be fully open from Wednesday 15th August 2018, according to the BBC.

15 August 2018

This road fully opened to traffic this morning.

More information

Routes
Region

With thanks to Gerry McKenna and Michael Pritchard for information on this page.